Edward Thompson
Hi Jay I doubt if a 1 metre section overlap would be sufficient , if the existing purlin is supported centrally(internal wall) along its length it would be fine to put another purlin from the chimney side to the central support (internal wall). Allow an overlap and bolt them together, the new purlin would sit slightly higher to ensure it sits tight against the rafters. The hardest bit would be getting the new purlin into the loft. If you are unsure it's probably best to post your job on the site. Hope this helps.Ed