Self levelling a garage floor

Posted by Andy Steward, on
I have just had my garage extended from single width to double, so now a floor area of 32sgm. Half of the floor is existing concrete and the new half has also had concrete layed to meet where the old floor finished. I am looking to use self-levelling compound across the whole floor so that there is no obvious transition and any imperfections can be hidden. How soon can i use this kind of compound on top of a "new" concrete slab? and how much much material should I need?
Alan Morris

Alan Morris

Hi Andy the coverage for most self levelling compounds is 4sqm per bag at a thickness of 3mm so based on that you would need 8 bags but if it needs to be thicker then adjust the quantity accordingly
Danny Allen

Danny Allen

I would give it at least 2/3 days and if you check the coverage on bag of self level compound to work out how many bags needed

What would you like to do now?

Find more questions Create my Job

Homeowner stories

Homeowner stories - Nick

Nick shares his story of finding local tradespeople in his new area.

app-icon

Get our app for homeowners

  • Send messages and get notifications from tradespeople
  • Add photos to get more accurate quotes
  • View tradespeople’s profiles