When is 50% of a bathroom refurb project deemed complete

Posted by Drew Heppenstall, on
I am in dispute with building contractor who claims that additional payment is due on the basis that 50% of the project (Complete bathroom refurb) is now complete. Based on the contracted tasks below is this project 50% complete? a) Remove old bathroom suite and tiles - Complete b) Move 3 pipes to be under floorboards - Complete (This part turned into replumbing all of the pipework under bathroom floor) c) Lay new water resistent floor boards - Not complete What has been laid has a large "burn mark" caused by plumber plumbing in the free standing bath taps in the wrong place! d) Fit Free Standing Bath Taps - Incomplete as they have been plumbed in the incorrect place. Despite telling exactly where they needed to be these have been plumbed in in the wrong place an damage caused to new floor panel e) Move light switch to outside and fit new light in ceiling - Not complete (Cable has been moved, switch attached but it is just hanging on the end, not attached to the wall, f) Plaster/skim the walls and the ceiling - Not started g) Tile the floor - Not started h) Tile the walls - Not started i) Fit the bath - Not started J) Fit the radiator - Not started K) Fit the toilet and sink - Not started L) Remove all of the rubbish - Incomplete this is all just piled up on front drive part in blue bags most not. Would appreciate any comments/advice especially as the contractor involved came from this site and I quote from him "Clearly you do not want to understand the process of this highly skilled and qualified job." Many thanks
David Knight

David Knight

Hi Drew You are right to be concerned if you feel that the work has not progressed to a point which justifies a further payment. '50%' complete is always going to be a little ambiguous, but on the face of what you've outlined here I would agree it's not at that point. The quote or estimate you received should itemise the labour and materials separately. If you've not already paid him for all of the materials then a request for this I would say is reasonable. I would suggest with the labour that you should go back to him with what you deem to be 50% complete (based on the list above). I would think it reasonable for that to include resolving the things that you are concerned about and maybe getting to half way through the tiling (which also allows you to gauge the quality of his finishing work)? If yourself and the contractor can maintain the conversation on a calm and professional level that always helps. Both parties should be willing to compromise but you shouldn't be pressured into making a payment that you feel is unreasonable. And as a last resort, as much as it may be an inconvenience, you can always walk away and progress with someone else.

What would you like to do now?

Find more questions Create my Job

Homeowner stories

Homeowner stories - Nick

Nick shares his story of finding local tradespeople in his new area.

app-icon

Get our app for homeowners

  • Send messages and get notifications from tradespeople
  • Add photos to get more accurate quotes
  • View tradespeople’s profiles